6.3 Cross travelling device
General Items
6.3.1 The allowable deviation for installation of single-rail cross travelling device shall comply with the requirements in Table 6.3.1(see Figure 6.3.1).
Quantity to be checked:100%.
Inspection method:See Table 6.3.1.
Table 6.3.1 Allowable deviation for installation of single-rail cross travelling device
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_3.jpg?sign=1738983316-sjLSUTp5bvaVxjrT9dren6yTq4pcjT1x-0-0c9aaf49c1078cb2af567093b0c4b7fc)
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_4.jpg?sign=1738983316-bf7gEY3YMcKpRT7vYCixPD8vTtoDthbX-0-a1ff28802cf341bb18093ca2b15bcd25)
Figure 6.3.1 Schematic drawing for installation of single-rail track and guide rail for cross travelling trolley
1-lower guide rail;2-upper guide rail;3-track
6.3.2 The allowable deviation for installation of double-rail cross travelling device shall comply with the requirements in Table 6.3.2.
Quantity to be checked:100%.
Inspection method:See Table 6.3.2.
Table 6.3.2 Allowable deviation for installation of double-rail cross travelling device
![img](https://epubservercos.yuewen.com/5DC1A6/18000635001102306/epubprivate/OEBPS/Images/txt006_5.jpg?sign=1738983316-LVmplXXFWVtPlWiz57HoCmINxG0KX3bs-0-652bce3e49d7b3e9a648dbd56904c686)